Marshall Avenue: Mississippi River Blvd to Cretin AvenueMarshall Avenue: Mississippi River Blvd to Cretin Avenue

Project Jurisdiction: 
St. Paul
Grant Amount: 
$490,800
Date of Funding Approval: 
June 2007
Expected Completion Date: 
August 2010
Contact the Project Manager 

Barb Mundahl
651-266-6112

Marshall Avenue Flyer

This project provided a sidewalk, an eastbound bike lane and "Bicyclists Allowed Full Use Of Lane" signs for westbound bicyclists on Marshall Avenue between Cretin Avenue and the Lake Street Bridge.

Other amenities include countdown timers at the two signalized intersections with pedestrian walk signs, planted medians, bus shelter, bike racks, improved lighting and a dynamic speed display sign.

 


South side curb construction

photos by Jamez L. Smith